City road projects for week of May 4

Starting Monday, May 4, weather permitting, and continuing all week, Smith Paving, subcontractor of DiGioia-Suberban Excavating, will be paving the Phase II areas of Bramley Road. Work will start in the far north end or the far east end of the subdivision go toward Brookside Road. The work will involve numerous concrete trucks taking up the only available lane of travel, moving at a very slow rate of speed, consequently impacting traffic from 7 a.m. to 5 p.m.

Paving upper Brookside Road is also scheduled to begin May 4, and followup work will take place May 5-6. Impacted driveways will be closed for three to four days. Residents will be required to share drives or park in designated temporary areas during the project. One-lane, one-way traffic will continue to travel southbound and westbound through the work zone.