Park board approves event planner position

by Sue Serdinak

Oct. 12 Richfield Joint Recreation District meeting

At the same meeting when Sheri Green’s resignation as the park’s event and venue coordinator was announced, Park Director John Piepsny recommended hiring a part-time employee to fill the position rather than using an independent contractor.

Piepsny said the Lodge and Amity House have been nearly fully booked during warmer months. The Lodge is rented primarily for weddings and Amity House for bridal parties.

Board Treasurer Dave Wehner reported that gross rental revenue from the Lodge totaled $232,000 last year.

The board approved a motion to create an event planner position with pay ranging from $18 to $30 per hour.

Board Chairperson Anita Gantner suggested creating a second half-time position to handle event setup and cleanup. Piepsny suggested paying that employee $20 per hour. No vote was taken.

Board member Steve McPeake supported the change.

Board member Cindy Moore asked whether the Richfield Heritage Preserve Conservancy could handle event setup. Gantner said the conservancy is a small group and could not handle the work.

Board member Mike Lyons reported that the governance committee had been asked to consider granting hiring authority to the park director.

“We have provided a possible amendment to the bylaws,” he said.

The proposed amendment would allow the park director to hire staff within staffing levels, compensation ranges and appropriations authorized by the board. The park director could also discipline or terminate employees in accordance with the board’s employment policies.

Lyons suggested that board members provide feedback on the amendment at the next meeting and adopt the change if they choose to do so.

Infrastructure

Piepsny reported that Amity House had been rented consistently for smaller groups, but rentals were halted after a toilet backed up. A maintenance employee could not clear the blockage, and a plumber found a diaper lodged in the pipe.

Piepsny said a video inspection revealed that the sanitary line had collapsed. He recommended replacing the line, which would require digging up the lawn, but said weddings could still be scheduled.

“We are in our prime season … and are jam-packed with weddings [at the Lodge],” said Piepsny.

Wedding parties often take photos on the lawn near Amity House.

“I don’t see how we cannot do this [work],” said Gantner.

Garfield Hall

Another park building may soon be available for rentals once an occupancy permit is obtained for Garfield Hall. The Friends of Richfield Heritage Preserve worked on the building for several months in 2024, but it has remained locked since then.

Piepsny reported that he requested architectural drawings from Friends President Corey Ringle and submitted them with an occupancy permit application.

North House

Piepsny said he applied for a $150,000 state capital grant to repair North House and received approval for $50,000. The Friends had previously volunteered to complete some of the work.

Fence repairs

The Friends also offered to remove fallen trees and repair damaged fencing along the park’s perimeter.

Piepsny said park maintenance staff were unavailable to provide the equipment the Friends needed. Park policy prohibits volunteers from using their own tools.

Dam leak

The upper lake is no longer leaking, according to Piepsny. He reported that a bladder inserted into the main drain about two months earlier was successfully holding back the water.

Piepsny said he requested bids from six companies to evaluate and permanently repair the leak. So far, only Davey Resource Group has submitted a bid for engineering services. Its estimate was $62,540.

Piepsny estimated that the entire project would cost about $250,000. He recommended that the board apply for a low-interest loan through the Ohio Dam Safety Program.

He said federal grant programs usually consider whether homes would be flooded if a dam failed. Earlier studies revealed that a dam failure in the park would flood only the golf course south of state Route 303.

Piepsny added that the state is trying to have dams removed because they are not good for the environment. He said the state has the final say on dam repairs.

Wick Poetry Center

Gantner asked the board to enter into a partnership agreement with the Wick Poetry Center at Kent State University to convert Cook’s Cabin into a residence for visiting artists. The cabin currently lacks running water.

The Wick Poetry Center would contribute $30,000 toward the project.

Piepsny said the estimated cost to install plumbing in the cabin is $50,000 to $60,000. He said developer Sam Petros and HTZ Construction helped evaluate additional improvements needed to make the cabin habitable. They estimated the total project cost at $100,000 to $200,000.

Piepsny said he thinks the Friends and Oviatt House volunteers “would pull together to get the work done.”

Gantner said the park’s conservancy had verbally committed to securing a donation for the project.

“Would the board agree to say we are in favor of the concept?” asked Gantner.

Other board members were not convinced.

“If we are going to be asking for money for this project, we will likely be asking for money for other projects,” said Holly Price.

“It is unclear what is [Wick Poetry Center’s] commitment to the program?” said Lyons.

McPeake said he would like the costs spelled out.

Gantner nevertheless asked the board to “give some thought to this and send your questions to John.”

Cleveland Restoration Society

Piepsny reported that the Cleveland Restoration Society sponsored a SNOOP tour of Richfield Heritage Preserve. Participants viewed restoration work at Kirby House, Kirby Mill, Garfield Hall and Oviatt House.

State Historic Preservation Office

Piepsny announced that the Friends recently received two SHPO Preservation Merit Awards for their work on Amity House and Garfield Hall. They will be recognized in Columbus on Nov. 6.

Oviatt House

Trisha Steiner gave a presentation on the restoration and construction work to convert Oviatt House into a museum. She showed photos of the museum’s interpretive design plan, developed by the organization with assistance from Benchmark Craftsmen.

The group plans to work with Benchmark on fabrication and installation of the displays. Volunteers will develop the exhibit content with assistance from Impact Communications.

The organization recently received a $7,500 grant from the Cynthia Woods Mitchell Fund. It also received a $40,000 grant from the National Park Service through its National Underground Railroad Network to Freedom program and the Association for the Study of African American Life and History.

The funds will pay for an ADA entrance ramp and a walkway to the parking lot.

Kirby Mill bridge

The park’s law director approved an agreement between the park and GFT Infrastructure to conduct a structural and safety assessment of the bridge crossing the dam at Kirby Mill.

The Friends agreed to pay the estimated $10,000 cost and requested inclusion in all communications with the engineering firm.