Brecksville Road projects target spring completion

by Dan Holland

Ongoing construction work along Brecksville Road continues at both the north and south ends of the city with two major infrastructure projects.

When completed, the travel lanes in the north end of town will meet Ohio Department of Transportation minimum lane-width standards. New sidewalks, an all-purpose path and a new traffic signal at Longano Drive will provide pedestrians and bicyclists improved safety, according to city engineer Don Ramm, while new LED lighting will provide better nighttime visibility. Residents and business owners along the stretches of road will have improved water quality and reliability with replacement of the 100-year-old water main.

North end

The Brecksville Road streetscape improvements project was awarded to Catts Construction in February, with work beginning in March. The $5.82 million project is expected to have a 12-month duration.

The project, which extends from Rockside Road to the intersection of Rockside Woods Boulevard North, consists of a water main replacement and several new components, including a 12-inch water main, fire hydrants, storm sewer improvements, water service connections, road pavement widening, concrete curbs, curb ramps that comply with the Americans with Disabilities Act, a 5-foot-wide sidewalk along the east side of the street, an 8-foot-wide all-purpose path along the west side of the street, concrete drive aprons, decorative streetlights, a mast-arm-style traffic signal with a pedestrian crossing signal at Longano Drive, an underground conduit and pull boxes to accommodate fiber optic lines and new mailboxes.

According to Ramm, the September project budget was nearly 60% expended, and the project itself was 56% complete, which indicates that project work is on schedule.

Ramm said the contractor is expected to install the widened pavement, curbs, drive aprons and sidewalks along the west side of the street this year prior to work being suspended for winter. Work will resume in the spring with concrete work, streetlight installation, grading and lawn restoration. Final completion is scheduled for late spring 2027. 

South end

At the south end of the city, Catts Construction was awarded a $3.47 million, six-month-long project in April designated as the Brecksville Road Phase 1 watermain replacement project. The project extends from East Sprague Road to the north side of the East Pleasant Valley Road intersection.

The south project includes a new 12-inch water main, fire hydrants, water service connections and underground conduits and pull boxes. Crews will repair storm sewers, catch basins and manholes and replace sections of concrete curbs, sidewalks, curb ramps and drive aprons where needed.

Through September, 55% of the project budget had been spent and work was 58% complete, Ramm said.

All water work, road pavement installation and related concrete curb, sidewalk and drive apron repairs along the east side of the road are expected to be completed by Thanksgiving, with substantial completion expected in early December, according to Ramm.

Final concrete work and lawn restoration will resume in spring 2027, when final completion is projected.